Front Gable with steel and framing complete |
Another update from site at Cyncoed Road. Kevin the builder has made excellent progress recently and the roof is almost fully complete - only some minor repairs and finishing work to do. The verges and window framing are in and resolve the problem of the poorly aligned steelwork very nicely. The expressed steelwork on the main gable elevation looks good, but we should have allowed it to stand proud of the blockwork so the render finished flush. This would have given a crisper result. However, the shaped and chamfered edge that Kevin has done works nicely with the more textured render visible on the original house.